CITY OF CHARLOTTE - MARY ALEXANDER ROAD REOPENED - Mary Alexander Road

What's Going On:
Mary Alexander Road has reopened to vehicular traffic (see updated information below)

When:
Tuesday, August 8, 2017 8:00 AM to Friday, August 18, 2017 5:00 PM

What to Expect:
- Sidewalks between Mallard Green Apartments and Lex Drive will remain closed
- Pedestrian traffic should continue to follow the detour route
- Periodic partial lane closures on Mary Alexander Road; delays are expected
- Both lanes will be open to vehicular traffic at the end of each construction day
- Heavy construction equipment
- Construction personnel/flagmen
- Signage
- Open holes and trenches
- It is important to note this is a City of Charlotte project

REMAINING WORK INCLUDES -
** Asphalt paving in front of Mallard Green Apartments (final surface with a lane closure)
** Construct large culvert headwalls (daily lane closure)
** Install small storm drainage run across Lex Drive (lane closure on Lex Drive and possibly Mary Alexander)
** Install sidewalk, curb, and gutter at the large culvert near Lex Drive (lane closure to install)
** Pave (asphalt) intersection at Lex Drive (lane closure)
** Install stream grade control structures (may need lane closure for materials delivery)

Why:
To perform necessary work as part of the City of Charlotte's Mary Alexander Storm Drainage Improvement Project
For any questions or concerns please contact mulrick@charlottenc.gov (Mike Ulrick) at 9802420634